Mechanical scope of work
1. HVAC Equipment
- 1.1
Furnish and install all ductless split system heat pumps, including indoor units, outdoor units, refrigerant piping connections, condensate pumps, mounting brackets, and all associated wiring.
Drawing refs4/M5.1510/M5.12E2.31E2.32M0.02M2.21M2.23M3.11M3.12 - 1.2
Furnish and install all electric ceiling heaters.
Drawing refsM0.02M2.21 - 1.3
Furnish and install all Energy Recovery Ventilators, including mounting hardware and accessories.
Drawing refs7/M5.11E2.32M6.01M2.22M3.11M3.12S3.21 - 1.4
Furnish and install all equipment platforms and supports.
Drawing refs6/M5.116/M5.1212/M5.111/M5.123/A5.41 - 1.5
Furnish and install all exhaust fans, including all required curbs, backdraft dampers, speed controllers, adjustable drives, motor covers, drain connections, grilles, enclosures, and mounting hardware.
Drawing refs7/M5.128/M5.111/M5.13M6.01M2.21M2.22M2.23M3.11M3.12S3.21 - 1.6
Furnish and install all fan coil units, including condensate pumps, safety switches, mounting brackets, and plenums.
Drawing refs6/P5.119/M5.1210/M5.12E2.32M0.02M2.21M2.22M2.23